CJM Construction v. Scott Mann
── CJM Construction v. Scott Mann ──
Case No.: 24A-SC-02488
Court: Indiana Court of Appeals
Date: November 18, 2025
Author: Judge Rudolph Pyle
County of Origin: Wayne
Category: Civil
Decision: Affirmed
Judge Bradford and Judge Kenworthy concur
In the summer of 2023, Mann hired CJM to renovate his house. CJM
estimated that the renovation would cost roughly $54,000, and Mann agreed to
that cost. CJM and Mann did not have a written contract. From July 2023 to
November 2023, Mann paid CJM $45,000, and CJM worked on the home
renovation. In December 2023, CJM sent an invoice in the amount of $6,629
to Mann. CJM considered this bill as a progress payment and had not
calculated a final estimate for the cost of the renovation.