Court: Court of Appeals for the Tenth Circuit
Date: May 29, 2026
Category: General
Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 1
FILED
UNITED STATES COURT OF APPEALS United States Court of Appeals
Tenth Circuit
FOR THE TENTH CIRCUIT
_________________________________ May 29, 2026
Christopher M. Wolpert
SJH 11 LLC, a Delaware limited liability Clerk of Court
company,
Plaintiff - Appellee,
v. No. 25-8037
(D.C. No. 1:25-CV-00018-SWS)
DOWBUILT, INC., a Washington (D. Wyo.)
corporation and John Does 1-10,
Defendants - Appellants.
_________________________________
ORDER AND JUDGMENT *
_________________________________
Before MORITZ and FEDERICO, Circuit Judges, and ALLEN, District Judge **.
_________________________________
During an arbitration between plaintiff SJH 11 LLC and nonparty SDI LLC—
which is ostensibly owned by defendant Dowbuilt, Inc.—the arbitrator ruled that SJH
was not required to arbitrate certain of its claims against Dowbuilt and instead could
file those claims in a court of competent jurisdiction. After SJH filed this action,
Dowbuilt moved to compel arbitration. The district court denied the motion and
Dowbuilt appeals.
*
This order and judgment is not binding precedent, except under the doctrines
of law of the case, res judicata, and collateral estoppel. But it may be cited for its
persuasive value. See Fed. R. App. P. 32.1(a); 10th Cir. R. 32.1(A).
**
The Honorable Ann Marie McIff Allen, United States District Judge for the
District of Utah, sitting by designation.
Appellate Case: 25-8037 Document: 32-1 Date Filed: 05/29/2026 Page: 2
We affirm. Contrary to Dowbuilt’s strained interpretation of the arbitrator’s
order, the arbitrator did in fact determine that SJH is not required to arbitrate the
claims at issue. Since the parties do not dispute that questions of arbitrability were
delegated to the arbitrator, we are bound by that arbitrability ruling.
Background
In 2021, SJH and SDI entered into two identical contracts related to the
development of two properties in Jackson, Wyoming. Although the contracts were
solely between SJH and SDI, SDI included a statement in each that it was doing
business as Dowbuilt. The contracts required all disputes to be first mediated and
then, if unresolved, arbitrated by the American Arbitration Association (AAA) in
accordance with its Construction Industry Arbitration Rules.
SJH terminated the contracts in September 2022. 1 It refused to pay SDI’s final
invoices, and SDI filed for arbitration in November 2023. Referring to itself in its
filings as either doing business as Dowbuilt or simply as Dowbuilt, SDI asserted
claims for breach of contract and unjust enrichment. In February 2024, SJH answered
and filed counterclaims against SDI for breach of contract, breach of the implied
covenant of good faith and fair dealing, and conversion.
On December 6, 2024, SJH filed a motion under Construction Industry
Arbitration Rule 9(a), which provides that “[t]he arbitrator shall have the power to
1
SJH’s complaint alleges that it did so because of what it viewed as SDI’s
suspicious billing practices. But its actual termination was for convenience based on
a contract provision permitting SJH to “at any time, terminate the [c]ontract fo
{# E23 (Nick, ruling section 1 answer 10): quoting a bill or a court opinion works
the way quoting a news article works. Select a passage above and the same panel
opens: the passage goes to the official you choose, with this document's own
address as its source and its own type. #}