Citizens of the State of Florida, Etc. v. Florida Public Service Commission
── Citizens of the State of Florida, Etc. v. Florida Public Service Commission ──
Court: Supreme Court of Florida
Date: June 04, 2026
Category: General
Supreme Court of Florida
____________
No. SC2023-0988
____________
CITIZENS OF THE STATE OF FLORIDA, etc.,
Appellant,
vs.
FLORIDA PUBLIC SERVICE COMMISSION,
Appellee.
June 4, 2026
FRANCIS, J.
The Office of Public Counsel (OPC) appeals the Public Service
Commission’s (the Commission’s) partial approval of Florida City
Gas’s (FCG’s)1 petition for a rate increase. 2 Specifically, OPC
challenges the Commission’s approval of two accounting measures
that impact FCG’s rate plan: (1) the Reserve Surplus Amortization
1. FCG is a utility company and subsidiary of Florida Power &
Light Company (FPL), serving residential, commercial, and
industrial customers in Miami-Dade, Broward, St. Lucie, Indian
River, Brevard, Palm Beach, Hendry, and Martin counties. It sells
and transports natural gas to customers.
2. We have jurisdiction. See art. V, § 3(b)(2), Fla. Const.
Mechanism-Adjusted Depreciation Parameters (RSAM-ADP); and
(2) the Reserve Surplus Amortization Mechanism (RSAM). OPC also
challenges the Commission’s continuation of an accounting
adjustment related to a corporate transaction, referred to as an
acquisition adjustment. We affirm.
I. BACKGROUND
In 2022, FCG petitioned the Commission, seeking approval of
a four-year rate plan. In relevant part, FCG’s petition sought
approval of the above-mentioned RSAM-ADP and the RSAM. The
continuation of an acquisition adjustment was not initially
addressed in FCG’s petition, but it became an issue during
litigation.
With respect to the RSAM-ADP, at the final hearing the
Commission considered three different depreciation proposals:
(1) FCG’s 2022 Depreciation Study, a mandatory depreciation
study; (2) the RSAM-ADP, FCG’s alternative depreciation study; and
(3) OPC’s proposed Depreciation Parameters. While each of these
proposals was based on slightly different underlying depreciation
parameters, according to FCG’s lead witness Ned Allis, each of
FCG’s proposals was within the “range of reasonableness.”
-2-
The RSAM-ADP—according to the collective testimonies of Mr.
Allis and Mark Campbell—was a reasonable alternative to the
traditional depreciation parameters and, if adopted, would provide
customers with rate stability and certainty and avoid repetitive and
costly rate proceedings. Liz Fuentes also testified that the RSAM-
ADP was based on depreciation parameters that were previously
approved by the Commission. Their individual testimonies are
further discussed below.
FCG, however, offered no testimony regarding whether the
RSAM-ADP complied with the Commission’s Depreciation Rule.3
Under the Depreciation Rule, when there is a reserve
deficiency or surplus4 because of proposed depreciation
parameters, two things must happen. First, a gas utility’s
depreciation study must explain and justify “any proposed transfers
3. See Fla. Admin. Code R. 25-7.045 (regulating gas utilities’
obligation to account for depreciation in the ratemaking process).
4. We have explained that “[a] depreciation reserve surplus
occurs when a company collects a higher amount than needed to
cover depreciation expenses given new information revealing that an
asset, like a plant, has a longer-than-expected service life.”
Floridians Against Increased Rates, Inc. v. Clark (FAIR), 371 So. 3d
905, 908 n.8 (Fla. 2023).
-3-
of reserve between categories or accounts intended to correct
deficient or surplus reserve balances.” Fla. Admin. Code R. 25-
7.045(5)(f). And second, the Commission should investigate “[t]he
possibility of [a] corrective reserve transfer[] . . . prior to changing
depreciation rates.” Id. R. 25-7.045(4)(e).
{# E23 (Nick, ruling section 1 answer 10): quoting a bill or a court opinion works
the way quoting a news article works. Select a passage above and the same panel
opens: the passage goes to the official you choose, with this document's own
address as its source and its own type. #}