Filed 5/28/26 Yu v. West Bend Mutual Ins. Co. CA4/3
NOT TO BE PUBLISHED IN OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
or ordered published for purposes of rule 8.1115.
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
FOURTH APPELLATE DISTRICT
DIVISION THREE
BANN-SHIANG LIZA YU,
Plaintiff and Appellant, G064542
v. (Super. Ct. No. 30-2009-
00255065)
WEST BEND MUTUAL
INSURANCE COMPANY, OPINION
Defendant and Respondent.
Appeal from a judgment of the Superior Court of Orange County,
William D. Claster, Judge. Affirmed.
Lex Opus, Mohammed K. Ghods, Jeremy A. Rhyne and Lori L.
Speak for Plaintiff and Appellant.
Kirtland & Packard and Robert A. Muhlbach for Defendant and
Respondent.
Since 2009, plaintiff Bann-Shiang Liza Yu has pursued claims
against multiple insurance companies for, inter alia, breach of the implied
covenant of good faith and fair dealing and for contribution following
settlements in a construction defect lawsuit filed over 20 years ago. Those
settlements included assignments to Yu of various parties’ rights to pursue
those insurers which did not participate in the construction defect action.
This appeal is from the judgment entered in favor of one of those
insurers, defendant West Bend Insurance Company, following a bench trial
on stipulated issues remaining in the case. The trial court issued a statement
of decision containing the court’s finding that neither Yu nor West Bend’s
insured, ATMI Design Build, provided West Bend notice of Yu’s construction
defect action against ATMI until well after Yu settled with ATMI. In light of
the notice and no-voluntary-payments provisions contained in the relevant
West Bend insurance policies and governing law, the court concluded Yu is
unable to recover against West Bend on any theory.
We affirm. Substantial evidence supports the trial court’s
findings on notice. Because those findings are dispositive as to West Bend’s
liability to Yu in this case, we do not address Yu’s challenges to other rulings
and findings by the court which limited the type and amount of recovery she
might have been entitled to had West Bend been provided notice.
FACTUAL AND PROCEDUAL HISTORY
I.
THE CONSTRUCTION PROJECT
In January 2002, Yu, a developer, entered into a contract with
ATMI to act as the general contractor for the construction of a hotel in
Anaheim (the project). (Yu v. West Bend Mutual insurance Company (Feb. 14,
2
2018, G053358) [nonpub. opn.] (Yu).) Construction on the project began in
September 2002.
In 2004, ATMI allegedly abandoned the project. Himes Peters
Jepsen Architects (HPJA), with which Yu had already contracted to act as
architects on the project, took over as the general contractor for the project.
(Yu, supra, G053358.)
II.
ATMI IS INSURED BY, INTER ALIA, WEST BEND
West Bend issued annual comprehensive general liability policies
to ATMI from June 30, 2000, through June 30, 2003 (West Bend policies).
(Yu, supra, G053358.) The West Bend policies contained provisions requiring
ATMI to notify West Bend as soon as practical if a claim is made or a lawsuit
is brought against it. The West Bend polici
{# E23 (Nick, ruling section 1 answer 10): quoting a bill or a court opinion works
the way quoting a news article works. Select a passage above and the same panel
opens: the passage goes to the official you choose, with this document's own
address as its source and its own type. #}