Cage Ranch Solar, LLC v. FERC
── Cage Ranch Solar, LLC v. FERC ──
Court: Court of Appeals for the D.C. Circuit
Date: May 19, 2026
Category: General
United States Court of Appeals
FOR THE DISTRICT OF COLUMBIA CIRCUIT
No. 23-1227 September Term, 2025
FILED ON: MAY 19, 2026
CAGE RANCH SOLAR, LLC AND CAGE RANCH SOLAR II, LLC,
PETITIONERS
v.
FEDERAL ENERGY REGULATORY COMMISSION,
RESPONDENT
SOUTHWEST POWER POOL, INC.,
INTERVENOR
Consolidated with 23-1304
On Petitions for Review of Orders of the
Federal Energy Regulatory Commission
Before: KATSAS and PAN, Circuit Judges, and GINSBURG, Senior Circuit Judge.
JUDGMENT
These petitions for review were considered on the record from the Federal Energy
Regulatory Commission and on the briefs and oral arguments of the parties. The Court has
accorded the issues full consideration and has determined that they do not warrant a published
opinion. See D.C. Cir. R. 36(d). It is now
ORDERED AND ADJUDGED that the petitions for review be DISMISSED.
* * *
Cage Ranch Solar, LLC and Cage Ranch Solar II, LLC (collectively, “Cage Ranch”)
petition for review of orders of the Federal Energy Regulatory Commission denying Cage Ranch’s
complaint and request for a waiver. Before the FERC, Cage Ranch argued that Intervenor
Southwest Power Pool, Inc. used a fundamentally flawed study model to assign network upgrade
costs to Cage Ranch. Cage Ranch also argued the FERC should waive the deadline by which
Southwest required Cage Ranch to post financial security to maintain its position in Southwest’s
interconnection queue. Before us, Cage Ranch argues the FERC failed to ensure the costs assigned
to it were just and reasonable and was otherwise arbitrary and capricious. We conclude that Cage
Ranch has failed to show it suffered an injury necessary to establish its standing, and we
accordingly dismiss the petitions.
I
Cage Ranch is the developer of a 900 MW solar generation project in Texas. In 2017, in
order to connect its project to the electrical grid, Cage Ranch submitted interconnection requests
to Southwest, a regional transmission organization. Southwest’s interconnection study process is
cluster-based and involves three phases. Following Phase 1 and Phase 2 is a “decision point,”
during which an interconnection customer must decide whether to post the required financial
security. Failure to do so within 15 business days results in withdrawal of the customer’s
interconnection request and loss of its position in the interconnection queue. At Decision Point 2,
the amount of financial security an interconnection customer must post is 20% of the network
upgrade costs assigned to that customer by the interconnection study, less the amount of any
security that customer has already provided.
Southwest assigned Cage Ranch’s interconnection requests to Group 5 of the 2017-002
study cluster. Southwest posted Phase 1 results for this group in February 2022, preliminarily
assigning $302 million in network upgrade costs to Cage Ranch. As required by Southwest’s
Tariff, Cage Ranch paid $4.19 million in financial security and proceeded to Phase 2. In August
2022, Southwest posted Phase 2 results, which allocated $311 million in network upgrade costs to
Cage Ranch. Cage Ranch would have had to post approximately $60 million by September 20,
2022 to proceed to Phase 3.
Rather than post the $60 million, on September 20, 2022 Cage Ranch filed a complaint
with the FERC challenging Southwest’s Phase 2 cost-allocation model as defective. Because
Southwest’s Tariff treats the failure timely to post financial security as a withdrawal, Cage Ranch
also sought a waiver of the deadline and withdrawal provisions in the Tariff while the FERC
conside
{# E23 (Nick, ruling section 1 answer 10): quoting a bill or a court opinion works
the way quoting a news article works. Select a passage above and the same panel
opens: the passage goes to the official you choose, with this document's own
address as its source and its own type. #}