Wildwood Builders v. Lee CA1/3
── Wildwood Builders v. Lee CA1/3 ──
Court: California Court of Appeal
Date: May 12, 2026
Category: General
Filed 5/12/26 Wildwood Builders v. Lee CA1/3
NOT TO BE PUBLISHED IN OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not
certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been
certified for publication or ordered published for purposes of rule 8.1115.
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
FIRST APPELLATE DISTRICT
DIVISION THREE
WILDWOOD BUILDERS, INC,
Plaintiff, Cross-defendant and
Respondent, A175009
v.
SHIUH-KAI LEE, as Trustee, etc., (Alameda County
Defendant, Cross-complainant Super. Ct. No. RG21097358)
and Appellant.
After a bench trial, the trial court concluded that Shiuh-Kai Lee, in his
capacity as trustee of the Lee-Wei Family Trust, breached his contract with
Wildwood Builders, Inc. (Wildwood) by refusing to pay a portion of its fees
after completion of repairs to his apartment building. He appeals, advancing
various theories of error. Finding none persuasive, we affirm.
BACKGROUND
In April 2021, Wildwood sued Lee alleging breach of contract after he
refused to pay sums due under their agreement. In June, he countersued and
alleged Wildwood breached by failing to fully perform. In his cross-
complaint, he alleged that Wildwood was, at “[a]ll relevant times,” a “licensed
contractor.”
1
In February 2020, Wildwood and Lee entered into an agreement under
which Wildwood would repair balconies at Lee’s apartment complex in
exchange for approximately $175,000. The agreement incorporated “Plans by
SDS Structural Engineering,” “phase II,” “[s]heet” “S10.0.” “Sheet S10.0
include[d] a plan sheet,” with “an arrow pointing to the bottom of a deck
section” and a note “that reads ‘(N) 5/8” Dens Glass Type-X Sheet Rock’ ” with
“ ‘Synthetic Finish Over Lay.’ ” (Some capitalization omitted.) The
agreement also explicitly excluded “labor or materials” for work including
“stucco,” “deck coating,” “paint,” or any “material except shop primed steel
beams.” (Italics omitted.)
The agreement provided that “final contract payment is due and
payable upon ‘Substantial Completion’ (not Final Completion) of all work
under contract.” It defined substantial completion “as being the point at
which the building/work of improvement is suitable for its intended use, or
the issuance of an occupancy consent, or final building department approval
from the city or county building department, whichever occurs first; for work
included in this contract” (capitalization omitted). In November 2020, the
city building inspector gave its “final ok pending completion of stucco.”
Wildwood did not apply a finish to the underside of the balconies, and Lee
withheld payment.
In 2024, the trial court held a six-day trial. Lee argued that the plans
incorporated into the agreement required Wildwood to install a synthetic
finish rather than stucco, and parol evidence was not necessary to interpret
the contract. Wildwood, for its part, argued that the agreement’s exclusion
clause included the synthetic finish because that is what contractors
“typically consider ‘stucco.’ ” At trial, the court heard parol evidence
concerning the meaning of stucco.
2
After the trial, the trial court concluded Wildwood fulfilled its
obligations, and Lee breached the agreement. It found that, “[d]espite the
dispute over the application of the synthetic finish,” Wildwood had
substantially completed the project. It also found stucco is an “external
coating system” including “a finish, plaster layer, a layer of self-furring lath,
and layers of wate
{# E23 (Nick, ruling section 1 answer 10): quoting a bill or a court opinion works
the way quoting a news article works. Select a passage above and the same panel
opens: the passage goes to the official you choose, with this document's own
address as its source and its own type. #}