Case No.: 24-3331
Court: Court of Appeals for the Second Circuit
Date: March 23, 2026
Category: General
24-3331
Allco Fin. Ltd. v. Roisman
UNITED STATES COURT OF APPEALS
FOR THE SECOND CIRCUIT
SUMMARY ORDER
Rulings by summary order do not have precedential effect. Citation to a summary order filed on
or after January 1, 2007, is permitted and is governed by Federal Rule of Appellate Procedure 32.1
and this court’s Local Rule 32.1.1. When citing a summary order in a document filed with this
court, a party must cite either the Federal Appendix or an electronic database (with the notation
“summary order”). A party citing a summary order must serve a copy of it on any party not
represented by counsel.
At a stated term of the United States Court of Appeals for the Second Circuit,
held at the Thurgood Marshall United States Courthouse, 40 Foley Square, in the
City of New York, on the 23rd day of March, two thousand twenty-six.
PRESENT: Debra Ann Livingston,
Chief Judge,
José A. Cabranes,
Steven J. Menashi,
Circuit Judges.
____________________________________________
ALLCO FINANCE LIMITED, CHELSEA SOLAR
LLC, and APPLE HILL SOLAR LLC,
Plaintiffs-Appellants,
v. No. 24-3331
ANTHONY ROISMAN, RILEY ALLEN, and
MARGARET CHENEY, in their official capacities
as commissioners of the VERMONT PUBLIC
UTILITY COMMISSION,
Defendants-Appellees. *
____________________________________________
For Plaintiffs-Appellants: THOMAS MELONE, Allco Finance Limited,
New Haven, CT.
For Defendants-Appellees: DAVID GOLUBOCK, Assistant Attorney
General, Office of the Vermont Attorney
General, Montpelier, VT.
Appeal from a judgment of the United States District Court for the District
of Vermont (Crawford, J.).
Upon due consideration, it is hereby ORDERED, ADJUDGED, and
DECREED that the judgment of the district court is AFFIRMED.
Plaintiffs Allco Finance Limited, Chelsea Solar LLC, and Apple Hill Solar
LLC (“Allco”) 1 sued the commissioners of the Vermont Public Utility
Commission alleging two violations of federal law. According to Allco,
(1) Vermont’s Standard Offer Program for utility contracts for certain qualifying
energy facilities is preempted by both the Federal Power Act, 16 U.S.C. § 791a et
seq. (“FPA”), and the Public Utility Regulatory Policies Act, 16 U.S.C. § 2601 et seq.
(“PURPA”), and (2) Vermont committed a taking in violation of the Fifth
Amendment when it adopted a statutory amendment rendering Allco’s Chelsea
Solar facility ineligible for the Standard Offer Program. The district court
dismissed the complaint on the grounds that (1) Vermont’s program is not
preempted and (2) Vermont’s regulations “do not reach the level of an
*The Clerk of Court is respectfully directed to amend the official caption as set forth
above.
1We refer to the plaintiffs collectively as “Allco.” Allco Finance Limited is the single
member of Chelsea Solar LLC and Apple Hill Solar LLC. See J. App’x 17 (¶¶ 46-47).
2
unconstitutional taking.” Allco Fin. Ltd. v. Roisman, No. 23-CV-691, 2024 WL
5276715, at *14 (D. Vt. Nov. 19, 2024).
But Allco previously litigated the question of whether federal law preempts
the Standard Offer Program before the Vermont Supreme Court. See In re
Investigation to Review Avoided Costs that Serve as Prices for Standard-Offer Program
in 2020, 215 Vt. 140, 142 (2021). Accordingly, we conclude that Allco’s preemption
claim is barred by collateral estoppel. We agree with the district court that Allco
failed to state a takings claim. We assume the parties’ familiarity with the facts,
procedural hi
{# E23 (Nick, ruling section 1 answer 10): quoting a bill or a court opinion works
the way quoting a news article works. Select a passage above and the same panel
opens: the passage goes to the official you choose, with this document's own
address as its source and its own type. #}